What should Doug Ford's government do about developers who go years without building homes?

The complaint: some developers have yet to put a shovel in the ground on some housing projects that have had all necessary approvals for years. The consequence: some cities face losing out on the province's $1.2 billion housing infrastructure fund because they won't meet the government's targets for new home construction starts in 2023.

Some Ontario cities want power to slap 'use it or lose it' penalties on stalled housing projects

Aerial view of an overgrown vacant lot and vehicles parked, with a light dusting of snow on the ground.
The Town of Newmarket approved rezoning of this property along Yonge Street to allow a high-rise development of more than 500 housing units back in 2018, but construction is yet to begin. (Michael Cole/CBC)

At least 20Ontario municipalities are so far away from reaching their provincially-mandated targetsfor new home construction starts that they havevirtually no chanceof hitting the mark, and will face stiff financial consequences in 2024.

The problem is something municipal politicians say puts Ontario atrisk of failing to meet the goal of 1.5 million new homes in a decade unless the provincial government does more to prod hesitant developers into starting construction.

Under current rules set by Premier Doug Ford's government, cities that fall short of the 2023 target for housing starts will not get any money next year from the province's $1.2 billion fund to help cover the costs of housing-related infrastructure.

Mississauga is among the municipalities most likely to miss its target. That's why city councillor Alvin Tedjo feels particularly frustrated when he looks across the half-empty parking lot of a shopping plaza that the city approved for housing a decade ago.

"I don't think it's fair at all that the province is measuring our success on housing starts and not on housing approvals," said Tedjo in an interview at the site. "We can't control whether or not the developer starts building the projects that we've already approved."

Tedjo is far from the only municipal politicianraising concerns about the role developers play in Ontario's housing crisis. They're pointing to housing projects that have all the necessary municipal approvals, but developers have yet to put a shovel in the ground.

Outdoor photo of Alvin Tedjo
Mississauga city councillor Alvin Tedjo says it's unfair that the provincial government is measuring success on housing starts and not on housing approvals. (Mike Crawley/CBC)

The nine municipalities in York Region, includingthe cities of Vaughan, Markham and Richmond Hill, have approved more than 49,000 housing units that are not yet under construction, according to data from the region's chief planner.

Figures from the City of Mississauga show construction has not begun on approved projects totalling more than 29,000 homes.

"We need to compel them to move forward," said Tedjo. "We need these developers and these landowners to show that they're interested in building."

'Use it or lose it' policy in the works

There is precious little that municipalities can do to compel a developer to build. Some cities are callingon the province to give them the power to impose some sort of penalty on approved projects that are stalled for unreasonably long periods, often called a "use it or lose it"policy.

The Ford government is developing a proposal along these lines, but Municipal Affairs and Housing Minister Paul Calandrais signalling that it won't involveslapping penalties on developers.

"We will work very closely together to make sure that we have an effective use-it-or-lose-it policy, one that is not punitive, but one that works foreverybody," Calandra saidin a speech this week at a housing forum with municipal, industry and non-profit leaders.

Calandra said municipalinfrastructure for such things as water and sewer lines should be made available to developers who are ready to build homes "without punishing" those who are not ready to start construction.

A wide-angle view of a parking lot partly filled with vehicles, with a shopping plaza in the background.
Mississauga city council approved this parking lot and plaza for housing 10 years ago, but the developer has yet to start building. (Mike Crawley/CBC)

The question this provokes in city halls around Ontario: why then is the Ford government taking a punitive approach to municipalities?

The government'sBuilding Faster Fund isa$1.2-billion pot of money to help municipalities cover housing-related costs, such as infrastructure.Only cities that come within 80 per cent of their annual target for new home construction in a given year will be eligible for the fund in the following year.

Calandrasaid Monday he is not considering changingthe rules on how municipalities qualify for the fund, but said all of the money will be used.

Newmarket Mayor John Taylor calls the policy not only unfair to municipalities, but also potentially damaging to the government's own plan for 1.5 million new homes by 2031, because he believes it willhamper the building of the water and sewerfacilities needed for housing.

Put some pressure on developers, says mayor

Taylor says it's wrong for the province to make future infrastructure funding contingent on past housing starts, which he contends is influencedfar more by market demand, interest rates, labour shortages and construction coststhanby any factor under municipal control.

"I'm not aware of one policy or one financial tool that has actually put pressure on developersas opposed to municipalities," Taylor said in an interview. "They're the ones positioned best to get things done, far better than we are."

John Taylor is sitting at his desk looking toward the camera.
John Taylor is mayor of the town of Newmarket. (Matthew Haggerty/Town of Newmarket)

He is concerned about property owners asking municipalities forzoning and planning approvals merely to push up the value of their land, with no intention to build homes.

"Not only is it a significant problem, but it's a problem that's been going on for a very long time," said Taylor.

Sunset clause, boosting development charges

Ontario's Big City Mayors, which represents cities with populations of 100,000 or more, have asked the province to give municipalities powers to try to spur developers into starting construction.

One suggestion is fora sunset clause on housing projects, allowing municipalities to revoke planning approvals if construction hasn't begun within a specified time period.

Another involves development charges, the fees that cities levy on projects to cover infrastructure costs. The Ford government has mandated that cities reduce these charges, but cities would like the power to boost the fees if a developer delays construction post-approval.

Indoor photo of Dave Wilkes.
Dave Wilkes is president and CEO of the Building Industry and Land Development Association (BILD), which represents developers in the Greater Toronto Area. (Robert Krbavac/CBC)

Dave Wilkes, president and CEO ofthe Building Industry and Land Development Association (BILD), rejects the notion that developers are fuelling the housing crisis by sitting on properties for too long.

"I don't think it is a contributing factor," said Wilkes in an interview."It's at worst a distraction, and at best a misdirection."

Why construction gets delayed

Wilkes says there are various legitimate reasons why construction may be delayed after approvals, such as financing fallingthrough, market demand shifting or construction costs rising.

He said the industry would like to find out from municipalities more specifics about which projects are stalled, why they aren't moving forward, and what needs to happen to get them going.

The province posted the latest figures on its housing supply trackerlast week, tallying new home construction starts as of the end of October.

The figures show that 23 municipalities are less than half-way to their 2023 target, and face losingout on the Building Faster Fund in 2024 barring a sudden rush of housing starts in November and December or a change in the government's criteria.

Townhomes under construction in the city of Barrie, Ont.
The Ford government has set a target of 1.5 million new homes built in Ontario over a 10-year period, for an average of 150,000 homes per year. (Mike Crawley/CBC)

They include some of Ontario's largest cities, such as Mississauga, Brampton, Markham, London, Windsor, Kitchener and Burlington.

The town of Newmarket is also well short of the mark: housing starts so far in 2023 amount to just seven per cent of its target.

Taylor, Newmarket's mayor,says there is a "misguided perception" that the municipal approval processis to blame for the slow pace of new home construction in Ontario.

"This narrative that the housing crisis lies at the feet of municipalities just does not hold up to scrutiny," he said. "If anybody believes that if you could reduce the planning process timeline by 30 per cent, then we wouldn't have a housing crisis,I think you're fairly naive."