City returns to appeals board seeking order to have Capital Pointe hole filled - Action News
Home WebMail Wednesday, November 27, 2024, 05:37 AM | Calgary | -14.1°C | Regions Advertise Login | Our platform is in maintenance mode. Some URLs may not be available. |
Saskatchewan

City returns to appeals board seeking order to have Capital Pointe hole filled

The City of Regina is asking yet again for a backfill order at the Capital Pointe construction site.

Westgate Properties did not take part in Friday's appeal board hearing

The City of Regina is once again trying to get the Capital Pointe hole filled. (Craig Edwards/CBC)

The City of Regina is asking yet again fora backfill order for the Capital Pointe construction site at the corner of Albert Street and Victoria Avenue.

CapitalPointewas first announced in 2009 and was set to become Regina's tallest building. It was originallyscheduled to be done by June 2015.

On Friday morning the Saskatchewan Building and Accessibility Standards Appeal Board held a limited appeal hearing to re-hear portions of previous testimony.

DanaeLemieux,senior traffic engineer with the City of Regina, said Westgatehad failed to renew or reapply for a street use permit (SUP). The permit allows a work site to use part of a roadway, sidewalk or other city property. Westgate has not had a valid SUP since March 2018, Lemieux said.

Westgate did not attend Friday's proceedings.

City of Regina Commercial Building Inspector Jeremy Chalupiak also spoke before the board. Chalupiaksaid he was in charge of inspecting the work site several times a month. He saidthat during his inspections from July to Decemberof 2018 no work had been done by Westgateat the site and thathe asked Westgate to file monitory reports on the work site but it failed to do so.

Chalupiaksaid he observed aberm in the north-west corner of the work site thathad been eroded by water draining from a nearby alley.

Christine Clifford, who represents the City, said monitory reports need to be conducted for the sake of keeping the project safe. In her words, "movements indicating imminent failure are in the millimetres" and Westgateis not monitoring the site.

There are no current or pending building permits for the site and no application has been made for an SUP.

The Capital Pointe project would be Saskatchewan's largest building if completed. (Craig Edwards/CBC)

Clifford said Westgatehas made noprogress on the project since a previous appeal in August of 2018. During that hearing the boardgave the developer three options:

  • To"commence, continue, and carry out construction of the project to completion," so long as construction resumed by April 1 2018 and was completed by March 2022.
  • To build permanentprotection to the shoring on the site.
  • To backfill the site.

Clifford asked that the board order Westgatetofill the hole over a period of two weeks and rule that, if Westgatefailed to do so,the filling of the hole be contracted out through Sask Tenders.

"The city doesn't desire to backfill this property. This is not our best case scenario. Our best case scenario scenario was a building," Clifford said.