LRT won't be ready to roll until 2019 - Action News
Home WebMail Friday, November 22, 2024, 03:19 PM | Calgary | -10.4°C | Regions Advertise Login | Our platform is in maintenance mode. Some URLs may not be available. |
Ottawa

LRT won't be ready to roll until 2019

For the second time this year, the consortium building Ottawa's $2.1-billion LRT system will miss its deadline to hand over the Confederation Line to the city.

Group building Confederation Line misses deadline for 2nd time this year

'A lot of people have been waiting'

6 years ago
Duration 0:39
Public transit riders in Ottawa react to the news that LRT won't be ready for passengers until 2019, despite promises by Rideau Transit Group the system would be up and running by this year.

You may be "Ready for Rail," but the city isn't.

For the second time this year, the consortium building Ottawa's $2.1-billionLRTsystem will miss its deadline to hand over the Confederation Line, putting lie to the city's ubiquitous marketing slogan.

That means instead of riding the rails by the end of this year, transit users won't board the new light rail trainsuntil sometime in the first few months of 2019,OC Transpoboss John Manconitold city councillorsMonday morning.

One of the city's new light rail trains parked at the future Tremblay LRT Station in Ottawa's east end. The city invited media for a first-ever ride-along Wednesday, April 25. (Giacomo Panico/CBC)

The revelation appeared to take some councillors aback.

"I think this is very disappointing news," said Coun. Stephen Blais, the transit commission chair who's rarely at a loss for words."I think alot of people I know anyway, I'm pretty angry right now, actually."

Currently, there is no new deadlinefor the handover.

Fewer trains, trial runs

Rideau Transit Group (RTG) was originally supposed to deliver the LRTsystem to the city last May, but in February the city announced the date would be pushed backsix months to Nov. 2.

A memo from the city's O-Train team to councillorsas recently asAug. 13 raised no red flags about the deadline.

But just four days later, Manconiadmitted the team,which includes a panel of independent transit experts,met with RTGbecause "we saw some things we did not like."

Coun. Stephen Blais, who chairs the transit commission, expressed anger over the LRT delay. (CBC)

Last Tuesday, RTGsaid it could keep the Nov.2 deadline, but only if it was allowed to "carve out" some requirements in the contract. According to Manconi, RTGproposed:

  • Not conducting 12 consecutive days of trial runs on the entire rail line.
  • Not opening the north-side entrance to the Rideau Station.
  • Running only 32 trains instead of all 34, because two still aren't equipped withcomputer modules needed to run properly.

Manconitold councillors he refusedRTG's overture.

Then around 6 p.m. Friday, he received a call from RTGwith a revamped schedule to deliver LRT by Nov. 30, butManconiwasskeptical the consortium can meet even that deadline.

RTG did not immediately respond toa request for comment.

Fare freeze? Route reversal?

Because of the delay, Blaissuggested freezing transit fares. OC Transpo fares were set to rise about 2.5 per cent in January, but councillors and Mayor Jim Watson appeared open to the idea of delaying that hike until LRT is running.

Other councillors called for the bus route changes that were made last weekend to berestored. Many routes were shortenedor reconfigured to connect withTransitway stations in anticipation of the LRTlaunch.

But now that light rail won't be running until the winter months, Couns. Catherine McKenney, Bob Monette and Allan Hubleyargued thatat least some of those bus routes be brought back.

OC Transpo boss John Manconi said RTG told him last week that it could only meet the Nov. 2 deadline if it didn't meet certain contract requirements. (CBC)

Manconipromised only to look at the possibility, but noted route changes take months to plan and arecomplex.

City looks to RTG to pick up costs

Freezing fares and reinstating bus routes are only a few of the costs the city could incur because of this delay.

OC Transposent 345 bus drivers layoff notices last month, but it will now need to keep drivers on longer than expected. Continuing to operate the bus system instead of the more efficient LRT will also cost the city more than expected, as will necessary road detours.

More than 360 bus drivers were given lay-off slips, but the city will have to try to keep them on now that the LRT is delayed. (Trevor Pritchard/CBC)

Watson said the city expects RTG to pick up the tab for the city'sextra costs caused by the delay. But who's responsible for what under the contract is open to interpretation. For example,RTG does not believe it's responsible for the Rideau sinkhole, or the city's related costs.

Coun. Diane Deans, who said she was "disappointed" but "not surprised" by the delay, asked the treasurer's office to prepare a detailed analysis of what the setback will cost the city.

$1M penalty

When RTGmissed its original May deadline, it escaped paying a $1-million penalty stipulated in the contract.

But this time around, the consortium will be expected to pay.

If RTGmisses the next deadline which has not yet been set it will be penalized another $1 million.

City officials, including the mayor, insisted the delay will have no impact on the $3-billion Phase 2 of LRT, the contract for which is to be signed bythe end of 2018.

Mayoral candidate Clive Doucetsaid if elected, he would wait until light rail was operating for a couple of monthsbefore signing the contract for the next phase.