Canada Science and Technology Museum asked for roof funding in 2010 - Action News
Home WebMail Saturday, November 23, 2024, 08:04 PM | Calgary | -12.0°C | Regions Advertise Login | Our platform is in maintenance mode. Some URLs may not be available. |
Ottawa

Canada Science and Technology Museum asked for roof funding in 2010

The closed Canada Science and Technology Museum had been asking the federal government for years to help fix a leaky roof whose 'lifecycle had come to an end,' according to documents obtained by CBC News.

Museum currently closed after leaks led to mould

The Canada Science and Technology Museum is set to reopen in 2017 with several major upgrades. Documents obtained by CBC News show museum officials had been asking for funding to address issues with its roof as early as 2010. (Pawel Dwulit/Canadian Press)

The closed Canada Science and Technology Museum had been asking the federal government for years to help fix a leaky roof whose"lifecycle had come to an end," according to documents obtained by CBC News through an access to information request.

The museum, which closed in September after leaks in the roof led tounsafe levels of mould in the air, had communicated its desire for a new roof at its 50-year-old Ottawa location as early as 2010.

In a timelineobtained through the information request, the museum saidit told the Department of Canadian Heritage for four consecutive years, beginning with the 2010-2011 corporate plan,about the roof and the funding needed to fix it.

An engineering assessment in 2010 also "revealed that the Museum's rooflifecyclehad come to an end and required replacement given the potential for roof failure."

Museum officials met with the department on Dec.17, 2013, to present four options: patch the roof and maintain the status quo, partially repair the roof, completely replace the roof or build a new, angled roof over the existing one.

The museum's presentation from that day shows a recommendation for a partial replacement (at a cost that's been blacked out) that would take a minimum of 16 to 17 months. A formal request was made to the Risk Management Reserve, and approval was given by Heritage Minister Shelly Glover to get another cost estimate.

Asubmission to the Treasury Board was in the works forthe last week of September when unsafe levels of mould caused the museum to be evacuated and closed Sept. 11.

49 distinct leaks in less than a year

That timeline was part of a packageof documents dated Sept. 22, 2014. The documents also included alist of all the leaks in the museum's roof and the areas affected.

One example:

"Water leaks all weekend closet between Connections and Innovations, 4 small leaks in Connections, Innovations, Biocomposite Plastics exhibition, Electrical Panels on south wall, in between walls of Energy and Technozone, Technozonecarpets soaked," said the entry for Jan.10-12, 2014, describing nine of the 49 distinct leaks reported from Thanksgiving weekend 2013 untilthe closure.

Some of those leaks meant parts of exhibits had to be closed or covered with plastic to protect them, includingwhen the museum was open.

"The cars wrapped in plastic!! Is this a morgue?" one museum visitor said, according toa quote included in a section of the Dec. 17, 2013, presentation.

False start on roof repairs

CBC News previously reported that a roof repair project for the museum was launched in October 2013, with a budget of $3.2 million over five years to remove asphalt, add insulation and re-seal, amongother fixes.

The museum's funding request said work was halted immediatelyafter workers found "advanced deterioration of the existing roofing materials and the presence of asbestos in the crumbling cement layer" when they started the project.

Museum CEO Alex Benay and regional minister John Baird were unavailable for comment earlier this week.

Last month Glover announced $80.5 million of funding for upgrades to the museum including a complete roof replacement, upgrading the facade and exhibit space and retrofitting it to better handle earthquakes and fires.

Documents received in the request said a new buildinghas been "contemplated" since the mid-1960s, and funding had been received in 2008 to start planning work on a new museum.

The museum is expected to re-open in 2017.