Macdonald Bridge Big Lift work to close span this weekend - Action News
Home WebMail Saturday, November 23, 2024, 02:16 AM | Calgary | -11.7°C | Regions Advertise Login | Our platform is in maintenance mode. Some URLs may not be available. |
Nova Scotia

Macdonald Bridge Big Lift work to close span this weekend

The Angus L. Macdonald Bridge in Halifax will be closed the last weekend before Christmas as the fourth deck section of the span is replaced as part of the Big Lift project.

Bridge officials still confident the deck replacement work will be done by late fall 2016

Big Lift Iron Workers

9 years ago
Duration 1:33
Working on the Macdonald Bridge's Big Lift is not for the faint of heart.

The Angus L.Macdonald Bridge in Halifax will be closed the last weekend before Christmas as the fourth deck section of the span is replaced as part of the Big Lift project.

It's been a month since the last section was installed.

"We had hoped to be much further ahead. We expected to be at the tower by now," said Jon Eppell, chief engineer for Halifax Harbour Bridges.

Eppell says it's taking longer for the work crews to figure out the various stages of the job.The latest delay was due to the replacement of bolts on the hanging cable bands.

The chief engineer for Halifax Harbour Bridges says work on the Macdonald Bridge is taking longer than expected as crews figure out the various stages of the job. He still expects the deck replacement will be done by late fall 2016. (Shaina Luck/CBC)

The machinethat lifts the deck sections up from the barge is attached to the cables.The bolt replacement work is done from inside what's called "cable crawlers."

"They had some challenges getting those working," Eppell said."It's kind of like being in a little dory hanging up in the air, so it's sensitive up there."

If the project continued at its current pace, it would take a year to complete 24 of the 46segments.

Bridge officials are still confident the deck replacement work will be done by late fall 2016.They believe the process will speed up once the learning curve for all aspects of the job is over.

Construction on the Big Lift will take a break over the holidays. There will beno daytime or overnight closures once the bridge opens on the morning of Dec.24until Jan.3.

"In spite of the fact that we haven't made as much progress as we'd like, everyone has been working very hard and they need a break," said Eppell.