The smell of money: CBRM sewage project comes in 26% under budget

Cape Breton Regional Municipality's public works director says CBRM got lucky with tenders going out before the pandemic raised the price of everything and before contractors got busy with massive provincial construction projects.

Public works director says tenders went out just before pandemic, contractors were not yet busy

A dump truck and bulldozer sit on a muddy field in front of a new building.
Cape Breton Regional Municipality's new Sydney Harbour West sewage treatment plant is nearing completion and the $58-million project is under budget by about $15 million. (Tom Ayers/CBC)

A sewage treatment project in Sydney Harbour is coming in under budget and that has officials in Cape Breton Regional Municipality thinking about starting another one.

CBRM is just finishing a sewage treatment project on the west side of Sydney Harbour.

The estimated cost was $58 million, but it's coming in about $15 million under budget.

Public works director Wayne MacDonald said it's rare for a large infrastructure project to generate about 26 per cent in savings.

"Well, certainly not as many times as we would hope," he said.

The Sydney Harbour West project includes new sewage collector lines and a new treatment plant for waste from homes and businesses in Sydney River, Westmount, Coxheath and the Sydport industrial park.

A man in a brown suit speaks into a microphone.
Public works director Wayne MacDonald says CBRM got lucky with the timing of its tenders for the project, coming just before the pandemic drove up construction costs. (Tom Ayers/CBC)

Since the pandemic, construction projects have been hit with higher costs and labour shortages, but MacDonald said CBRM got lucky with the timing of the tenders on the latest project.

"We were at a very interesting time, just at the beginning of the pandemic late 2019, early 2020, before all of those effects really hit."

In addition, bids were competitive because contractors had not yet started work at massive reconstruction projects at area hospitals and the new Nova Scotia Community College campus in downtown Sydney, MacDonald said.

The municipality has already completed one large project cleaning up the east side of Sydney Harbour and has works underway in Glace Bay and Port Morien as it races to meet federal wastewater regulations.

A few years ago, CBRM started planning and getting cost estimates for a separate sewer treatment in New Victoria, further out in Sydney Harbour, so officials have begun talking with federal and provincial funding partners.

MacDonald said they seem positive about using the savings from the latest project to get the new one underway.

'In the ballpark'

"We upgraded those costs based on a bit of inflation to get us to a 2024 number and it's just shy of about $14 million, so we're in the ballpark, I believe," he said.

If the New Victoria project gets approved, MacDonald said it will go a long way towards improving the health of the harbour.

"It's another check mark for all of the raw water outfalls that we currently own and we're talking about 840,000 litres of raw sewer entering Sydney Harbour on a daily basis, so it's significant."

MORE TOP STORIES

Add some good to your morning and evening.

Get the latest top stories from across Nova Scotia in your inbox every weekday.

...

The next issue of CBC Nova Scotia newsletter will soon be in your inbox.

Discover all CBC newsletters in theSubscription Centre.opens new window

This site is protected by reCAPTCHA and the Google Privacy Policy and Google Terms of Service apply.