All-season road between Tibbitt Lake and Lockhart Lake moves forward despite dwindling diamonds - Action News
Home WebMail Friday, November 22, 2024, 08:37 PM | Calgary | -11.3°C | Regions Advertise Login | Our platform is in maintenance mode. Some URLs may not be available. |
North

All-season road between Tibbitt Lake and Lockhart Lake moves forward despite dwindling diamonds

Work on the all-season road between Tibbitt Lake and Lockhart Lake will begin in 2024. The road is the first piece of a larger gravel road that will run through the Slave Geological Province where the Ekati, Diavik and Gahcho Kue diamond mines operate.

Project hopes to support resource exploration, developmental activities and future economic growth, says gov't

Aerial photo of an opening mining pit in the winter.
A file photo of the Diavik diamond mine. Work on the winter road between Tibbitt Lake and Lockhart Lake will begin in 2024. The road is the first piece of a larger gravel road that will run through the Slave Geological Province where mines Ekati, Diavik and Gahcho Kue operate. (Diavik Diamond Mines)

The first phase of a plan to build an all-season road towardthe diamond mines is trucking ahead.

The Government of the Northwest Territories plans to begin geotechnical investigations this winter for the construction of the Lockhart all-season road.

The road is the first piece in a larger gravel road that will run through the Slave Geological Province a large, resource-rich area northeast of Yellowknife to connect the region and its resources to the Canadian highway system.

The territory submitted an application for a land-use permit through the Mackenzie Valley Land and Water Board in October, with the hope of assessing gravel quarries and other material for the road.

While the territorial government moves forward with its geotechnical investigations, another assessment through the Mackenzie Valley Review Board is awaiting a start date.

Originally requested by the TchGovernment, the assessment seeks to establish a development strategy and environmental framework for the region.

'The train has left the station'

Former MLA for Frame Lake, Kevin O'Reilly, said he's glad to see a more substantial plan for the region. During his term, O'Reilly called particular attention to the declining numbers of Bathurstcaribou in the area, and the impacts further industrialization could have on those numbers.

O'Reilly said declining diamond mines, along with the expensive and risky nature of resource exploration make developing the corridor a gamble with little benefit.

"What else could this money do for communities and job creation?" he said.

"Presumably, it's going to be billions of dollars of public money, spent on a road that could possibly lead to some more mineral developmentof questionable value."

Man in dress shirt and moose hide vest looks at camera.
Former MLA Kevin O'Reilly said developing the corridor is a gamble with little benefit. He said the public money could be better spent elsewhere. (Mario De Ciccio/Radio-Canada)

O'Reillysaidhe didn't see why the territory would push forward with the Lockhart Road before the regional assessment was complete.

"The whole reason for this study is so we don't make mistakes and take away opportunities for future generations that are irreversible," he said.

Mark Cliffe-Phillips, the executive director of the Mackenzie Valley Review Board,told CBC News the projects are working in tandem but said he couldn't comment further until the details of the assessment were finalized.

Cliffe-Phillips saidthe geotechnical work planned by the territory will be given a preliminary screening to assess environmental impact.

CBC News reached out tothe N.W.T. Department of Infrastructure for more information about how the two assessments are linked.

A spokesperson for the territorial government said in an email Wednesday that data from planning and design, including geotechnical investigations"will be useful in advancing the RSEA[Regional Strategic Environmental Assessment of the Slave Geological Province]."

In the same email, they said the federal government has indicated the RSEA has no intent of interrupting existing or planned regulatory processes in the Slave Geological Province,or pre-planning work.

A pathway to economic development

Tom Hoefer, theexecutive director of the NWT and Nunavut Chamber of Mines,acknowledges the enormous infrastructure costs of the project, and saida remote mine needs to be of higher quality to be truly economic.

A man standing
Tom Hoefer, the executive director of the N.W.T. and Nunavut Chamber of Mines, said the project would 'rejuvenate' exploration investment and help the mines last longer. (Travis Burke/CBC)

He saidhe thinks developing the Slave Geological Corridor would help the diamond mines last longer.

"There are more diamonds out there," he said. "But we have to rejuvenate exploration investment and interest to find them, and we have to get costs down in remote areas if we want to add to successful mining

"Should we give up now? I'd say no."

When finished, the Slave Geological Corridor will span 413 kilometresfrom Tibbitt Lake to the border between the N.W.T. and Nunavut.

Three diamond mines currently operate in the Slave Geological Province: Ekati, Diavik and Gahcho Kue. According to a territorial socio-economic report in 2020, the mines contributed $23 billion to the N.W.T.'s gross domestic product between 1996 and 2020.

Corrections

  • An earlier version of this story misspelled Tibbitt. The initial headline also inaccurately referred to the project as a winter road.
    Nov 29, 2023 11:47 AM CT