Contract to complete Muskrat Falls transmission system surpasses $500M - Action News
Home WebMail Friday, November 22, 2024, 10:14 AM | Calgary | -10.8°C | Regions Advertise Login | Our platform is in maintenance mode. Some URLs may not be available. |
NL

Contract to complete Muskrat Falls transmission system surpasses $500M

A combination of missed deadlines, change orders and settlements has pushed the cost of completing the transmission system on the Labrador-Island Link beyond the half-billion-dollar mark.

Original 2014 contract has increased by 30%

This is an aerial photo of the utility station at Soldiers Pond, on Newfoundland's Avalon Peninsula. The station converts direct current power transmitted over the Labrador-Island Link from Muskrat Falls to alternating current energy that can be integrated into the island's power grid. (Submitted by Nalcor Energy)

A combination of missed deadlines, change orders, protests and settlements has pushed the cost of a contract to readythe Labrador-Island Link for operation beyond the half-billion-dollar mark, CBC News has learned.

And documents show there is still risk associated with the contract as the Muskrat Falls project inches closer to completion.

An access-to-information request by CBC News has revealed that the originalcontract to construct converter stations, transition compounds and a specialized computer software forthe 1,100-kilometre high-voltage, direct-current transmission linefrom central Labrador to Newfoundland's Avalon Peninsula has grown by 30 per cent, to $519 million.

It's another example of how the price tag of Muskrat Falls has grown from $7.4 billion at sanction in 2012, to just over $13 billion, and why it was labelled "misguided" by Justice Richard LeBlanc, who led a commission of inquiry into the project.

This is a February 2020 photo of the synchronous condensers at the Soldiers Pond converter station, which is where electricity from Muskrat Falls is converted from DC to AC so it can be integrated into the island's power grid. The condensers are used to generate or absorb power as needed in order tomaintain optimal energy flow during the conversion from DC to AC, but have been plagued by vibration problems. (Submitted by Nalcor Energy)

According to a breakdown of the cost escalation provided by Nalcor Energy, the provincial energy corporation that oversees the project, a decision to make contractor GE Grid Solutions responsible for the civil work added $60 million to the contract value.

Nalcorexplained that it resulted in a streamlined management structure under one contract instead of two, and the additional cost was already included in the overall project budget.

A decision by Nalcorto changecourse and allow electricity to flow early over one conductor line, which first occurred in 2018, and energize the second line later, cost more than $32 million, while Nalcor has paid out more than $17 million in settlement claims to GE.

Protests against the project in October 2016 added $12 million to the cost of delivering transformers to Muskrat Falls and Cartwright, according to Nalcor.

Glitchy software

Nalcor inked a deal with a French company called Alstom in March 2014 at a value of just under $370 million, with a target to finish the work by the summer of 2017.

The contract called for the construction of a station at Muskrat Falls to convert electricityfrom AC to DC, two shore-based transition compoundsfor the undersea cable that crosses the Strait of Belle Isle, and a second station at Soldiers Pond to convertthe electricity back to ACfor integrationinto the provincial power grid.

Another critical part of the contract is the development of the computer softwareneeded tooperate the line, which has a capacity of 900 megawatts.

This is a breakdown of the extra charges that has resulted in a substantial escalation in the contract to make the Labrador-Island Link transmission line ready for operation. The contract is being carried out by a company called GE Grid Solutions, and its value has grown by nearly 30 per cent. (Nalcor Energy)

But like just about every other aspect of the project, the cost and schedule for the contract has been upended in a big way, beginning with Alstom's acquisition by General Electric in 2015, with subsidiary GE Gridtasked with completing the contract.

For years, the computer software has been plagued by glitches,and three synchronous condensers atSoldiers Pondcontinue to undergo modifications to repair vibration problems.The condensersgenerate or absorb power as neededtomaintain optimal energy flow during the conversion from DC to AC.

The latest update from Newfoundland and Labrador Hydro to the province's utility regulator earlier this month set a date of July 29 for the delivery of the final software, which is a further five-week delay from an earlier update. Further delays "remains a risk," according to Hydro, but trial operations using both power lines on the link known as "bipole" have been ongoing throughout the winter and spring.

As for the condensers, all three are notscheduled to be fully operational until September, just two months before the entire project is scheduled to achieve full commercial operations.

A steel electrical tower in the middle of a snowy field on a clear day.
The Labrador-Island Link comprises roughly 3,200 steel transmission towers like the one pictured here. It crosses some 400 kilometres of terrain in Labrador, includes a 30-kilometre link beneath the Strait of Belle Isle, and another 700 kilometres in Newfoundland. Up to last fall, some $3.6 billion had been spent building the energy corridor. (Terry Roberts/CBC)

The Labrador-Island Link is the energy corridor that will bring Labrador electricity to Newfoundland, and to Nova Scotia and beyond via the Maritime Link.

The link comprises some 3,200 towers, 2,300 kilometres of conductor wire, and the 30-kilometre subsea cable across the Strait of Belle Isle.

According to a recent quarterly report from Nalcor, some $3.6 billion has so farbeen spent building the Labrador-Island Link.

CBC News requested an interviewMonday with Nalcor CEO Stan Marshall, and is awaiting a response.

Read more from CBC Newfoundland and Labrador