STM's new AZUR Metro train remains rare sight - Action News
Home WebMail Tuesday, November 26, 2024, 02:17 AM | Calgary | -14.9°C | Regions Advertise Login | Our platform is in maintenance mode. Some URLs may not be available. |
Montreal

STM's new AZUR Metro train remains rare sight

With only one of Montreal's long-awaited new Metro trains in service for the next two months, Montrealers will need to know where to look or have a little bit of luck to hop on an AZUR train.

Single new 9-car train will be in operation on Orange line during non-peak hours for next 2 months

The STM's new AZUR cars are being built by the Bombardier-Alstom consortium. (STM)

With only one of Montreal's long-awaited new Metro trainsin service for the next two months, Montrealers will need to know where to look or have a little bit of luck to hop on an AZUR train.

Although the STM has been testing thenew trains since last August, the first nine-car trainwas put into regular service on Sunday.

"It was a very moving moment,"STM chairman PhilippeSchnobbtold CBC Montreal's Daybreak on Monday.

"You had people who were there 50 years ago for the very first ride, and they said, 'I had to be there for the first train.' It's very unusual to get a standing ovation when a metro gets into a station. We had that yesterday."

TheAZURcars will eventuallyreplace the iconic blue and white MR-63 cars that have been in service since 1966.

The 468 new cars are being built by theBombardier-Alstomconsortium for $1.2 billion.

Operating during non-peak hours

For at least the next 60 days, however, only one of the trains will be in operation on the Orange line during non-peak hours, Schnobb said.

"You have to be lucky because it takes an hour and a half to do [the full circuit], so every 45 minutes you'll get the train in your station," he said.

Or you could follow along on social media, Schnobb suggested,where many are sharing their impressions of the new trains when they spot them.

Schnobb said the trains remainin the testing phase and for now they won't be used during rush hour.

The new trains have greatercapacity, better lighting and improved ventilation, Schnobb said.

Eventually, more trains will be added to the Orange line, easing the congestion seen during rush hour, hesaid.

The trains must run for 61 consecutive days without a significant issue before the STM introduces another train, meaning the next one could be in operation in another two months. The full fleet of cars are scheduled to be delivered by 2018.