Judge approves City of Winnipeg's request to add defendants to police HQ lawsuit - Action News
Home WebMail Friday, November 22, 2024, 07:19 PM | Calgary | -11.4°C | Regions Advertise Login | Our platform is in maintenance mode. Some URLs may not be available. |
Manitoba

Judge approves City of Winnipeg's request to add defendants to police HQ lawsuit

The lawyer representing a Winnipeg company and its owner failed to convince a judge to keephis clients offthe list of defendants in a lawsuit over the construction of the downtown police headquarters building.

Chief Justice Glenn Joyal also rejected a motion requesting the city pay 2 defendants court costs

A wide shot of a glass-fronted building in Winnipeg's downtown.
The downtown Winnipeg police headquarters project was completed in 2016, years behind schedule and more than $79 million over budget. A Manitoba judge has approved the city's request to add more defendants to its lawsuit alleging fraud in the construction project. (Tyson Koschik/CBC)

The lawyer representing a Winnipeg company and its owner failed to convince a judge to keephis clients offthe list of defendants in a lawsuit over the construction of the downtown police headquarters building.

Lawyer Bob Sokalski argued that a motion from the City of Winnipeg in its ongoing lawsuitcontained no hard evidence against his clients, G&G Interiors Ltd. and its owner, Pietro(Peter) GiannuzziSr.

"There is nothing in these paragraphs that says, 'This is what G&G did,'"Sokalskisaidat a hearing in Manitoba Court of Queen's Bench Tuesday.

All of the city's allegations instead point to actions of Caspian Constructionthe contractor hired by the city to oversee the police headquartersproject andhave nothing to do with G&G or GiannuzziSr,Sokalski told the court.

"Caspian did this,Caspian did that. There is no accusation that G&G did anything fraudulent," he said, arguing a defendant accused of fraud is entitled to be told what they are alleged to have done.

He was arguing against a request ina notice of motion filed May 4, in which the city asked Chief Justice Glenn Joyalfor leave to amend its statement of claim in the lawsuit,originally filed in 2020against more than twodozen defendants.

The lawsuitalleges a schemeto inflate and overcharge the city for constructioncoststhrough fraudulent quotes and invoices, altered quotes from subcontractors and kickbacks related to the police headquarters aprojectcompleted in 2016, years behind schedule and more than $79 million over budget.

The original suit was filed a month after the RCMP ended a five-year investigation into the construction project, with nochargeslaid. A judge later approved the city's requestfor copies of thedocuments seized by the RCMP during the police probe.

Company was paid only what it was owed: lawyer

In the city's May 4 affidavit, aforensic accountant hired by the city toauditthoserecords said he found Caspian claimed nearly $8 million for G&G invoices related todrywall work on the police headquarters.However, Caspian payments to G&G totalled less than $6 million.

Sokalski argued that his clients were paid only what they were owed.

After listening to his submissions, Joyal granted the city'smotion.

In explaining his decision, he said that another group ofdefendants collectively referred to in the city's court filings as the "Garcea group" defendantsalso unsuccessfully opposed the city's motion.

In most fraud cases, the evidence is circumstantial, Joyal said, but the city should be given the opportunity to prove its allegations.

"It is important for the court to contextualize those allegations as being part of a circumstantial theory, as it touches all the defendants," said Joyal.

He said there aresome "direct, factual allegations" that have already been presented by the city against some of the other defendants.

"It'sagainst those defendants the city then draws its circumstantial theory as it relates to others," said Joyal.

2 defendants deniedcourt costs

The chief justice also dismissed a motion by two defendants, who were hired as consultants on the headquarters project, tohave the city pay their legal costs.

LawyerIvan Holloway, who is defending Peter Chang and Patrick Dubuc, arguedhe and his clients have repeatedly told the city they do not havedocuments related to the construction projectthe city continues to request.

"We have nothing more to produce," Holloway said in court, arguingthere should be consequences for what he described as the city's "one-size-fits-all" strategy with the defendants.

Holloway said the city's refusal to accept his client's positionled tohours of related work that produced no additional documents, and arguedthe city should have topay the $7,000 inresulting legal fees.

Michael Finlayson, a lawyer for the City of Winnipeg, said the city received 13 additional documents from Chang and Dubucon June 21,which they failed toproduce sooner, even though the city had been requesting documents for months.

A composite photo shows headshots of two men.
Peter Chang, left, was the principal engineer at Adjeleian Allen Rubelli (AAR) in Ottawa. His firm was awarded $4.8 million in sole-sourced contracts to complete the design on the Winnipeg police headquarters. Patrick Dubuc, right, is an associate at GRC Architects in Ottawa. His firm worked alongside AAR. (AAR/GRC Architects)

The city had been seeking a copy of a confidentiality agreement supposedly signed by Dubuc, Chang and Caspian owner Armik Babakhaniansto no avail.

The city says it learned of this agreement through emails obtained by the RCMP duringtheir five-year investigation.

In previous court filings, the city submitted an email Chang wrote to Ossama AbouZeidanproject director hired to look after the city's interests on the headquarters project.

In the email,AbouZeidaskedChang and Dubuc for documents to support an excess$20 millionrequested by Caspian for the HQ project.

According to Finlayson,Chang told AbouZeid"we have also agreed to sign a confidentiality agreement and to return our copies of all the documents to support an extra $20 millionsought by Caspian."

Chang said that was becausethebid information from Caspian was"proprietary and could hurt Caspian's tender negotiating abilities for future project bids tenders," according toFinlayson.

Chang and Dubuc were supposed to be looking out for the city's best interests, he argued.

But instead, they withheldinformationthe city needed toevaluate the request for an extra $20 million "because of an agreement to be signed with Caspian, who they are supposed to be monitoring and reviewing," said Finlayson.

He said as a result of repeated requests for documents, the city finally got some new information from Dubuc.

In a June 28affidavit to the court,Dubuc wrote that while "a confidentiality agreement relating to maintaining subcontract quotes confidential was contemplated by Armik Babakhanians. Mr. Babakhanians provided no such draft agreement to me and, accordingly, no such agreement was executed."

Dubuc's affidavit also says he has disclosed all the documents in his possession. He says a few years ago his computer "ceased to operate" and all the information contained on it was lost.

With files from Bartley Kives and Joanne Levasseur