Old Edmonton coal mine could delay construction of new school - Action News
Home WebMail Tuesday, November 26, 2024, 03:41 AM | Calgary | -14.8°C | Regions Advertise Login | Our platform is in maintenance mode. Some URLs may not be available. |
Edmonton

Old Edmonton coal mine could delay construction of new school

Construction of Ivor Dent School could be up in the air because of what lies beneath: an old coal mine.

Ivor Dent School scheduled to open in September 2017

The proposed site for Ivor Dent School in the Rundle Heights neighbourhood in the city's northeast end. (Supplied)

Construction ofIvor Dent School could be up in the air because of what lies beneath:an old coal mine.

At one time coal kept this city going. Now it might beanobstacle to new development.

Prior to the introduction of natural gas, coal wasused to heat homes in Edmonton.

With the fuel conveniently buried underneath the city, it resulted in more than 150 mines of varying sizesbeing dug between 1880 and 1970.

When the use of coal faded out, some old mines were simply boarded up and forgotten, only to be discovered years later.

That could be the case atthe site of a future replacement school in Rundle Heights, according to Brian Fedor, assistant deputy minister with the Learning Facilities DivisionofAlberta Infrastructure.

"They (environmental consultants) were able to find an actual registration of the mine that was registered in 1905 and then closed in 1925," he said.

Seismic tests will be conducted

There is a map of the old mine but Fedor isn't sure how reliable it is.

"The map accuracy in those days was general, no GPS for sure," said Fedor, adding that they will be conducting tests to figure out what exactly is under the ground on the proposed school site.

"One is to determine or confirm if there are any methane issues associated with the mine, and number two is to determineif there are geotechnical or structural issues related to the mine. In other words, do any of the mine tunnels come underneath the site?"

If coal-minetunnels do encroach on the site there are solutions.

"One of the things we could do is just extend our structural footings and/or pilings,"Fedor said.Another option could be to fill it with concrete, "that could be a possibilitydepending on how big the mine is."

That decision will likely come after officials get the results ofseismic tests at the end of March. That could delay the start of construction set for April, but Fedoris optimistic that even if that does happen, Ivor Dent School will still open as scheduled in September2017. The school would host650 students from kindergarten to Grade 9.

"I'm actually very confident of that at this point in time because the technical solution does not look like it would be very complicated. Nowadays the technology and the ability to mitigate these types of things is very comprehensive."