Construction set to take flight at Blatchford next summer - Action News
Home WebMail Tuesday, November 26, 2024, 07:42 AM | Calgary | -17.5°C | Regions Advertise Login | Our platform is in maintenance mode. Some URLs may not be available. |
EdmontonVideo

Construction set to take flight at Blatchford next summer

After installing more than eight kilometres of water, drainage and thermal heating pipeline under Blatchford this year, the city expects housing construction to begin by summer.

Utilities are in, housing is next for western section of former City Centre Airport lands

'There's a lot of people that want to live here'

7 years ago
Duration 1:16
City of Edmonton updates progress of Blatchford after one year of on-site construction.

After installing more than eight kilometres of water, drainage and thermal heating pipeline under Blatchfordthis year, the city expects housing construction to begin by summer.

The installationcompletesthe first year of a 20-year project aimed at housing 30,000 people in what the city billsalow-carbon sustainable community.

Withthe builder selection process endingnext week, developmentmanager Mark Hall says "the city is making exactly the kind of progressit was intending to do."

Watch the video edited by digital producer Trevor Wilsonfor the latest update.