Arena construction on time and on budget, says city report

The site has been excavated, the concretes been poured, and the new downtown arena is on track to be ready to open on September 2, 2016, according to a report by the city.
Construction continued on the Rogers Place arena downtown. A new city report suggests the project is on schedule and on budget. (Laura Osman/CBC)

The site has been excavated, the concretes been poured, andthe new downtown arena is on track tobe finishedSeptember 2, 2016, according to a report by the city.

Edmonton has already spent about 27 per cent of the $332 million they have committed for construction.

The city will request$25 million this month from the Alberta Community Partnership Program, which provides grants to projects that benefit communities.

They also planto ask formore fundingfrom other provincial and federal sources.

Construction has also begun on the new community rink, which will be part ofdevelopment.

Community rink also part of project

City administration has started giving some thought to how the facility will operate once the ice is ready.

The Edmonton Oilers will occupy the rink on weekdays, and McEwanUniversity will be on the ice in late afternoons. The rest of the time will be used for community programming.

The city also began a traffic study to look at the volume of cars driving downtown on game nights.

Council will review a report on the arenas progress on Tuesday.