Keystone XL pipeline builder asks judge to allow some work

The company that wants to build the Keystone XL pipeline is asking a U.S. judge to change his order blocking the project to allow pre-construction work to continue, such as purchasing materials and finalizing contracts.

TransCanada wants to keep preliminary work on track so pipeline work could start mid-February

TransCanada, the company that wants to build the Keystone XL pipeline, is asking a U.S. judge to change his order blocking the project to allow pre-construction work to continue, such as purchasing materials and finalizing contracts.

Attorneys for the company will argue in a Wednesday telephone conference that U.S. District Judge Brian Morris should clarify or amend his ruling to say the injunction does not apply to activities such as finalizing contracts, purchasing materials, conducting land surveys and discussing federal permits.

TransCanada wants to keep that preliminary work on track so that the Calgary-based company can be prepared to start pipeline construction as early as mid-February.

Blocking the pre-construction work even for several weeks would likely cause the company to miss the entire 2019 construction season and delay its 2021 target for oil to start flowing through the pipeline.

"A one-year delay in construction of the pipeline would result in substantial harm to TransCanada, as well was to United States workers, and to TransCanada's customers relying on the current in-service date of the project," TransCanada Pipelines Ltd. senior vice-presidentNorrie Ramsay said in a written statement to the court.

A year-long delay would cost TransCanada $949 million in earnings and put off the hiring of about 6,600 workers for construction, Ramsay said.

On Nov. 8, Morris blocked TransCanada's permit to build the pipeline from Alberta's oil sands through a half-dozen U.S. states to the Gulf of Mexico.

The judge had ruled that President Donald Trump's administration had not fully considered the environmental effects of the pipeline.

TransCanada's attorneys say the company is considering appealing Morris's order.

Ramsay also estimates that it could take as long as the first quarter of 2019 for federal agencies to complete the review ordered by Morris.

One group that sued to block the pipeline project, the Northern Plains Resource Council, declined comment on TransCanada's request, spokesman Dustin Ogdin said.

The attorney for another plaintiff, Indigenous Environmental Network, did not respond to a voicemail requesting comment.