Site C set to 'move a river' to build mega dam in northern B.C. - Action News
Home WebMail Thursday, November 21, 2024, 10:27 PM | Calgary | -10.9°C | Regions Advertise Login | Our platform is in maintenance mode. Some URLs may not be available. |
British Columbia

Site C set to 'move a river' to build mega dam in northern B.C.

BC Hydro is poised to divert part of a major river to build the $10 billion Site C mega dam in northern B.C.

About 15,000 fish affected as Peace River temporarily diverted for $10 billion BC Hydro project

The completion of two river diversion tunnels means the Peace River can be rerouted by early autumn, said BC Hydro. (Submitted by B.C. Hydro)

BC Hydro is poised to divert part of a major river to build the $10-billion Site C mega dam in northern B.C.

For years, the project has faced vocal opposition and controversy.

Now, Site C is just a few months away from rerouting the Peace Rivernear Fort St John, a temporary measure that could last up to five years.

BC Hydro says the completion of two giant diversion tunnels means the river canbe rerouted by late summer or early fall.

It says diverting the river willcreate a 500-metre stretch of dry riverbed, where construction can take place on dry ground for the construction of Site C's giantearth-fill dam.

"What you have to do to move a river is to build another path," said Dave Conway, BC Hydro's community relations manager for the Site C project."That's the work we've been doing for twoyears. It takes a lot of work."

That work wasconsidered so essentialthat hundreds of workers have remained on site to prepare for river diversion, despite the COVID-19 pandemic.

The diversion tunnels are about 750 metres long and 10 metres in diameter, according to BCHydro. They'll be able to carryup to 3,000 cubic metres of river water per second.

A graphic from a BC Hydro document shows how the Peace River will be diverted around the area of the Site C dam's construction. (BC Hydro)

The diversion of the Peace Riverwill impactabout 15,000 bull trout, mountain whitefish, Arctic graylingand other species, which are to be sedated andtrucked around the impasse, through what the company calls a "temporary fish passage."

"They're put in to a water tanker truck and then we move the fish around the construction site and deposit them upstream," said Conway.

BC Hydro says it will also monitor the risk of fish being stranded if water levels decline. With mitigation measures, the company says there will be "minimal impacts to wildlife."

A four-kilometre stretch of the Peace River is also being permanently closed to boaters this month.BC Hydro says it is offering a free shuttle service to help people in canoes and kayaks portage that stretch of water.

A river flows behind a small structure.
The Peace River, upstream from the Site C construction area. (Josh Pag/CBC )

Chief Roland Wilson of the nearby West Moberly First Nations saidit's difficult to watch the construction transform the Peace River valley.

"It's just a continuing quagmire of ugliness going on down there," Wilson said. "It's devastating to watch."

West Moberly is party to a lawsuitarguing that Site C irreparably harms its way of life andbreaches its treaty rights. The lawsuit seekscompensation or an order to shut downSite C and return the river valley to its natural state.

A photo from February shows crews constructing circular linings for the diversion tunnels. (BC Hydro)

Lawyer Tim Thielmann, who is acting for the West Moberly First Nations, said the case is set to go to trial in 2022.

"There will be time for judgment prior to the final inundation," said Thielmann.

Theriver diversion is set to continue until Site C's dam is complete, which is scheduled for 2024 or 2025.

Once that happens, Site C is expectedto generate enough electricity to power the equivalent of 450,000 homes.

Thousands of workers are being employed to build the multi-billion-dollar Site C dam. (BC Hydro/Contributed )